Summary
Developers will build about 8,700 feet of 12-inch water main to the ETJ boundary and be partially reimbursed, extending a key transmission line under the city's water master plan.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 27, 2026.
Impact analysis
The city will partially reimburse the developers for construction costs as invoices are received.
Residents and future development in the Yukon Road and Midway Boulevard area gain water transmission capacity.